Azerbaijan says to be “ahead of schedule” on TANAP

  05 September 2016    Read: 1631
Azerbaijan says to be “ahead of schedule” on TANAP
The work within the Trans-Anatolian Natural Gas Pipeline (TANAP) project is underway in accordance with the plan, President of the Azerbaijani State Oil Company SOCAR Rovnag Abdullayev told reporters Sept. 5.
He said, no problems are detected in the implementation of the project.

“Partly, we are even ahead of schedule and 850 kilometers of pipes have already been welded,” Abdullayev said.

Financing is not a problem as long as the projects are viable and doable, he added saying that the government use special incentives to attract external investors.

More about:  


News Line