"The new gas platform at the Guneshli field will become the first one in the history of independent Azerbaijan, the design and construction of which was fully implemented by SOCAR," said Abdullayev.
The platform is designed for drilling of 20 wells (six gas wells and 14 oil wells). It is planned to daily extract 100 tons of oil and 15,000 cubic meters of associated gas from each oil well, 150,000 cubic meters of gas and 15 tons of condensate from gas wells, according to estimates. The project cost slightly exceeded 180 million manats, most part of which, i.e. 111 million accounts for construction work.