“The latest activities include the commencement of the major lift programme despite the disruption caused by COVID-19, the arrival of the drilling derrick at the yard, with all three sections of the derrick already safely offloaded from the barge and positioned at the site’s construction location. Construction of the drilling modules is currently ongoing.
At the Heydar Aliyev Baku Deepwater Jackets factory (BDJF) the pin piles have been completed, successfully loaded out and driven into the seabed ready to receive the platform jacket. The jacket fabrication continues, as does the work on the subsea structures.
Engineering and procurement works remain on track to support the first production from the ACE project in 2023, with the larger equipment now moving from the suppliers into Azerbaijan,” the company said.