Azerbaijan completes reinforced concrete work on second water reservoir in Jabrayil

  28 October 2024    Read: 717
Azerbaijan completes reinforced concrete work on second water reservoir in Jabrayil

Concrete works in Azerbaijan's Jabrayil on the second water reservoir with a capacity of 1,000 cubic meters have been completed, and insulation works are ongoing, AzVision.az reports, citing the State Water Resources Agency of Azerbaijan.

The main line with a diameter of 280 mm and length of 1,177 meters, security room, and other facilities are fully ready.

"The first reservoir has passed testing and has been put into operation. A sewage line with a length of 5,300 meters and a diameter of 600 mm has been laid at the city exit," reads the report.

In the north of Jabrayil city, it is planned to drill a total of 9 sub-artesian wells, including 3 at the initial stage: "Currently, the control room of sub-artesian well No. 6, which has a capacity of 12 liters per second, has been put into operation."

 

AzVision.az


More about: Azerbaijan   Jabrayil  